Power / substation transformer
160+ weeks
↑ Elevating
Distribution / pad-mount transformer
30 weeks
↑ Elevating
Medium-voltage switchgear
44 weeks
↑ Elevating
Low-voltage switchgear
54 weeks
→ Stable

The index

Lead times for new orders across the U.S. market. Sourcing and method are detailed below.

EquipmentCurrent lead timeTrendHistory
Power / substation transformer160+ weeks↑ Elevating
Distribution / pad-mount transformer30 weeks↑ Elevating
Medium-voltage switchgear44 weeks↑ Elevating
Low-voltage switchgear54 weeks→ Stable
Generator step-up (GSU) transformer144 weeks↑ Elevating
Switchboards32–41 weeks→ Stable
Panelboards21–32 weeks→ Stable
Busduct / busway27 weeks→ Stable
Circuit breakers (commodity)In stock→ Stable

Order books: the leading indicator

Where supply is heading. A book-to-bill above 1.0 means orders are outpacing shipments, so the queue is still growing. Expand a row for its trailing trend.

ManufacturerBook-to-billTrailing trendReported backlog
Powell3.0$2.4BMV/LV switchgear
3.02.151.32025-08-052026-08-03

Backlog $2.4B (MV/LV switchgear) · book-to-bill 3.0 · as of 2026-08-03 · “data center order with a value exceeding $400 million” · source

Vertiv2.9$15.0B
2.92.051.22024-07-242026-02-11

Backlog $15.0B · book-to-bill 2.9 · as of 2026-02-11 · “data center demand” · source

GE Vernova1.7$40.6BElectrification
2.52.11.72026-04-222026-07-22

Backlog $40.6B (Electrification) · book-to-bill 1.7 · as of 2026-07-22 · “data centers, more than all of last year” · source

Siemens Energy1.48€51BGrid Technologies
2.281.881.482025-06-302026-06-30

Backlog €51B (Grid Technologies) · book-to-bill 1.48 · as of Q3 FY2026 · “power & GSU transformers, HV switchgear” · source

ABB1.39$13.7BElectrification
1.441.231.012025-06-302026-06-30

Backlog $13.7B (Electrification) · book-to-bill 1.39 · as of Q2 2026 · “triple-digit data center order growth, no pre-ordering” · source

Siemens1.25€23.7BSmart Infrastructure
1.01.31.150.992025-06-302026-06-30

Backlog €23.7B (Smart Infrastructure) · book-to-bill 1.25 · as of Q3 FY2026 · “switchgear, switchboards, busway” · source

Eaton1.2+43% YoYElectrical
1.21.151.12025-08-052026-07-31

Backlog +43% YoY (Electrical) · book-to-bill 1.2 · as of 2026-07-31 · “data center momentum” · source

Generac$1.6B

Tracking started. The trend line fills in as new quarters are captured.

Backlog $1.6B · book-to-bill not disclosed · as of 2026-07-29 · “data center backlog provides visibility to significant 2027 growth” · source

nVent$2.6B

Tracking started. The trend line fills in as new quarters are captured.

Backlog $2.6B · book-to-bill not disclosed · as of 2026-05-01 · “data center growth in both the gray and white space” · source

Schneider Electric€21.3BEnergy Mgmt

Tracking started. The trend line fills in as new quarters are captured.

Backlog €21.3B (Energy Mgmt) · book-to-bill not disclosed · as of FY2025 · “Square D parent; backlog +21% YoY” · source

Hitachi Energy$63.6B

Tracking started. The trend line fills in as new quarters are captured.

Backlog $63.6B · book-to-bill not disclosed · as of Q1 FY2026 · “large power transformers, HV switchgear; backlog +10% in one quarter” · source

Hammond Power Solutions+96.9% YoY

Tracking started. The trend line fills in as new quarters are captured.

Backlog +96.9% YoY · book-to-bill not disclosed · as of Q2 2026 · “dry-type & distribution transformers” · source

Macro pulse

Two measures of order-queue pressure. Industry order backlog divides Census M3 unfilled orders by one month’s shipments for NAICS 3353, electrical equipment manufacturing, giving the months of ordered-but-undelivered work the industry carries. Monthly since 1992, and computed here from the two component series: Census publishes a ready-made ratio only for the broader NAICS 335. ISM Supplier Deliveries surveys purchasing managers across all manufacturing and is inverted, readings above 50 indicate slowing deliveries.

Industry order backlog5.47 mo1.71× pre-2020NAICS 3353
7.075.032.992018-07-012026-06-01

Census M3 unfilled orders ÷ monthly shipments, electrical equipment manufacturing · latest 5.47 months (2026-06-01) · versus a 3.2-month average across 2017–2019, and a peak of 7.07 in 2022-10. Census publishes a ready-made ratio only for the broader NAICS 335, which includes appliances, lighting and wire; that series reads 4.03. Computed by Vawn from A35CUO ÷ A35CVS.

ISM Supplier Deliveries58.9above 50 = slower
60.654.9549.32025-08-012026-07-01

ISM Manufacturing Supplier Deliveries Index · latest 58.9 (2026-07-01) · trailing 12 months · readings above 50 mean deliveries are slowing.

Sources & methodology

This index aggregates public data and is refreshed regularly. See also our companion analysis: why electrical equipment prices won’t come down.

  • Siemens (CompAS Lead Time Adjustments): manufacturer-published lead times for LV switchgear, switchboards, panelboards, busduct.
  • Wood Mackenzie: T&D supply-chain survey. The substation transformer figure is Wood Mackenzie’s 2026 read of above 160 weeks. Its last published per-equipment survey, from Q2 2025, put power transformers at 128 weeks, GSU transformers at 143–144 and switchgear at 44; the GSU and switchgear rows still carry those Q2 2025 figures.
  • NEMA: distribution transformer lead times and domestic-capacity figures.
  • IEA: transmission-grid equipment lead times (largest units up to ~4 years).
  • Company SEC filings (EDGAR): Eaton, Powell, Vertiv, GE Vernova, nVent, Generac, Hubbell. Backlog and book-to-bill, normalized across quarters. Not every manufacturer quantifies both every quarter, several name data centers as the demand driver without stating either, so a figure carries forward from the last quarter that stated it, labelled with that date rather than presented as current.
  • Manufacturer investor relations (foreign filers, not on EDGAR): Schneider Electric, ABB, Siemens, Siemens Energy, Hitachi Energy, Hammond Power Solutions. Order backlog and book-to-bill from each company’s latest published results; segment book-to-bill is orders ÷ revenue where a company publishes only a group ratio. Schneider quantifies its backlog only at full-year results, so its row still carries the FY2025 figure.
  • Census M3 Manufacturers’ Shipments, Inventories and Orders: unfilled orders (A35CUO) divided by monthly shipments (A35CVS) for NAICS 3353, Electrical Equipment Manufacturing, months of ordered-but-undelivered work, monthly since 1992. Census publishes a ready-made ratio only for the broader NAICS 335, which folds in appliances, lighting and wire; the gear-only ratio shown here is computed by Vawn from the two component series.
  • ISM Manufacturing Report On Business: Supplier Deliveries Index (rolling 12-month series).
  • Distributor inventory: public stock availability for commodity breakers and panels.